Victorian payment schedule checks
Checks for a Victorian payment schedule: the 10 business day period, what the schedule must state, and the Commission's statement of the consequence of missing it.
- Kind
- Checklist. Steps or checks to work through and tick off.
- Where it applies
- Victoria
- AI use
- Yellow You and the tool draft together, with you directing. You check every statement you rely on.
- Law stated as at
- 22 October 2026
- Status
- Maintained. Checked on 22 October 2026 against the authority it cites, for Victoria.
- Version
- 1
- Source
- Written for this library
When to use it
Use when a respondent has been served with a Victorian payment claim and does not agree to pay the claimed amount by the due date. If the respondent agrees, the Commission page says to pay the amount in full on or before the due date.
Used for these tasks
- Draft the payment schedule and adjudication response
- Check AI-drafted payment claims and schedules against the security-of-payment Act
Each task page says how far AI may help with the task and what the lawyer must review.
How AI may be used
AI may calculate the tenth business day from the service date once the lawyer has set what a business day is under the Act. It must not write the reasons for withholding.
AI may
- Enter the date the payment claim was served and list a candidate tenth business day for the lawyer to confirm
- Check that a draft schedule identifies the claim and states a scheduled amount
- Flag a draft that gives no reason where the scheduled amount is less than the claimed amount
AI must not
- Must not write the reasons for withholding or for a lower amount
- Must not decide the due date for payment
- Must not say that a missed schedule can be cured except by recording the section 18(2) step the Commission describes
The lawyer checks
- Business day is counted as the Act counts it. This page does not define the term
- The contract is checked for a shorter period than 10 business days
- Each reason is one the respondent can support from the contract and the facts
Method: how the Green, Yellow and Red levels are decided. This is guidance for planning, not legal advice.
Read the full text
The full text is available after you log in. It is free. When you log in you can:
- read the whole precedent, with its drafting notes beside it;
- copy it, or download it as a Word file or Markdown;
- add it to your firm’s knowledge base, so colleagues can find it;
- let the AI tools you connect read it from that knowledge base.
The summary, the law it rests on and the AI-use guidance above stay public. Privacy.
More in Construction & Infrastructure
- Application for a commercial building dispute (QCAT Form 25)
- Building and construction dispute (State Administrative Tribunal): completion guide
- Residential building defects notice and claim letter (statutory warranties, NSW)
- Security of payment: payment claim (NSW base, with Victorian, Queensland, NZ and UK variants)
- Victorian payment claim checks
- Application for a domestic building dispute (QCAT Form 26)
- Residential building dispute application (TASCAT): completion guide
- Notice of dispute under a construction contract (AS 4000 family and bespoke contracts)
- Security of payment: payment schedule with reasons for withholding (NSW, with Queensland and Victorian notes)
- Deed of novation of a design consultant to a design and construct contractor
- Application for a debt recovery proceeding (QCAT Form 27)
- Residential building review (TASCAT section 58 form): completion guide
- Queensland adjudication application (QBCC approved form): preparation guide
- Victorian domestic building warranties schedule
- Scott schedule for an ACAT building dispute: completion guide
- Response and counter-application (QCAT Form 36)
- Notice of delay and claim for extension of time under a construction contract
- Covering letter to a principal contractor serving a payment withholding request (NSW)
- Queensland project trust and retention trust register
- Contract clause: AI-generated design, BIM data and practitioner responsibility
- Request for a decision by default, unliquidated damages (QCAT Form 50)
- Disciplinary application, building work contractors (SACAT): completion guide
- Queensland direction to rectify record
- Alleged defective or incomplete work schedule (QCAT)
- Protocol for AI use in expert delay and quantum analysis (construction disputes)
- Sample terms of settlement (VCAT building and property list)
All precedents for Construction & Infrastructure · Tasks and AI use in this area