Notice · Construction & Infrastructure
Notice of delay and claim for extension of time under a construction contract
Contractor's notice of delay and extension of time claim, structured to meet typical standard-form requirements: the qualifying cause, critical delay, days claimed, supporting analysis and reservation of rights.
- Kind
- Notice. A formal notice to serve or publish.
- Where it applies
- Australia
- AI use
- Yellow AI can help in set ways. A lawyer checks specific points before use.
- Law stated as at
- 17 October 2026
- Status
- Maintained. Checked on 17 October 2026 against the 2 authorities it cites, for Australia.
- Version
- 1
- Source
- Written for this library
When to use it
Use as soon as the contractor becomes aware of a delay or likely delay to practical completion, and again for the formal claim, under an Australian standard-form or bespoke construction contract. Follow the contract's notice clause exactly; this precedent does not replace it.
How AI may be used
AI may draft the notice and claim from the programme, site diaries and correspondence; the lawyer checks the contractual notice requirements, time bars and the delay analysis before service.
AI may
- Build a chronology of the delay event from site diaries, RFIs, directions and correspondence, with references.
- Extract every notice requirement, time bar and form requirement from the contract into a table.
- Draft the notice and claim in the contract's required structure for the lawyer to check.
AI must not
- Must not prepare or adjust the critical path delay analysis presented as expert evidence.
- Must not decide whether a time bar has been missed or whether the prevention principle applies.
- Must not serve the notice.
The lawyer checks
- The notice is given to the right person, by the right method, within the contractual period.
- Every precondition in the EOT clause is addressed (qualifying cause, actual delay to practical completion, notice content).
- The days claimed are supported by a programme analysis the contractor can stand behind.
- Delay costs and other entitlements are claimed or reserved as the contract requires.
Method: how the Green, Yellow and Red levels are decided. This is guidance for planning, not legal advice.
Read the full text
The full text is for signed-in accounts. It is free. When you sign in you can:
- read the whole precedent, with its drafting notes beside it;
- copy it, or download it as a Word file or Markdown;
- add it to your firm’s knowledge base, so colleagues can find it;
- let the AI tools you connect read it from that knowledge base.
The summary, the law it rests on and the AI-use guidance above stay public. Privacy.
More in Construction & Infrastructure
- Security of payment: payment claim (NSW base, with Victorian, Queensland, NZ and UK variants)
- Security of payment: payment schedule with reasons for withholding (NSW, with Queensland and Victorian notes)
- Queensland adjudication application (QBCC approved form): preparation guide
- Contract clause: AI-generated design, BIM data and practitioner responsibility
- Protocol for AI use in expert delay and quantum analysis (construction disputes)