Letter · Construction & Infrastructure

Covering letter to a principal contractor serving a payment withholding request (NSW)

Letter from a subcontractor's lawyers enclosing a payment withholding request under s 26A of the NSW Security of Payment Act: explains the principal contractor's duty to retain money, the 10-business-day notice if it owes nothing, joint liability for paying out, and when the duty ends.

Kind
Letter. A letter or email you adapt and send.
Where it applies
New South Wales
AI use
Yellow AI can help in set ways. A lawyer checks specific points before use.
Law stated as at
18 October 2026
Status
Maintained. Checked on 18 October 2026 against the 3 authorities it cites, for New South Wales.
Version
1
Source
Written for this library

When to use it

Use when a claimant has made an adjudication application against a respondent who is owed money further up the contract chain, and serves the approved-form payment withholding request on the principal contractor. The request itself is the approved form with its statutory declaration; this letter accompanies it.

How AI may be used

AI may fill the covering letter from the adjudication application and the contract chain and diarise the claimant's follow-up duties; the lawyer checks who the principal contractor is and the amounts, and the claimant makes its own statutory declaration.

AI may

  • Fill the parties, project, payment claim and adjudication application details from the file
  • Diarise the claimant's duties: serve the determination within 5 business days of receiving it, and give notice of any withdrawal within 5 business days
  • Build the contract chain table from the subcontract and head contract documents on file

AI must not

  • Must not draft, fill or outline the statutory declaration that the approved-form request must include
  • Must not alter the approved form or state amounts different from the adjudication application
  • Must not tell the principal contractor that it owes the respondent money unless the claimant has a basis for saying so

The lawyer checks

  • An adjudication application has been made for the payment claim before the request is served (s 26A(1))
  • The person served is a principal contractor within s 26A(4): someone by whom money is or becomes payable to the respondent for the relevant work
  • The request is on the form approved by the Secretary and includes the claimant's own statutory declaration (s 26A(2) and (3))
  • Service method and proof of service are in place, and the follow-up duties in ss 26B(5) and 26D(3) are diarised

Method: how the Green, Yellow and Red levels are decided. This is guidance for planning, not legal advice.

Authorities

Read the full text

More in Construction & Infrastructure

All precedents for Construction & Infrastructure · Tasks and AI use in this area