Check an ACT payment claim against the current Act before it is given

MaintainedLast reviewed

Key facts

Human involvement
RedLawyer-led
How AI is used
Extract the calendar month, the claimed amount, the contract payment day and the description of the work into a checking list.
What the lawyer must review
  • Confirm the Act covers the contract
  • Check the calendar-month timing
  • Use the earlier of the two section 13 dates as the due date
  • Approve the claim that is given
Written for / version
Australian Capital Territory versionACTAUNZUSNSWQLDVICTASWASANT

Rules that apply

The document starts from the task name. Change it if this piece of work is different.

The work product

Forum. Australian Capital Territory

Produce. A checklist for one payment claim, with the section 15 contents and the earlier section 13 date marked by the lawyer.

Have ready. The construction contract and the draft payment claim; Building and Construction Industry (Security of Payment) Act 2009 (ACT), Republication No 14; The ACT Government security-of-payments page; The Legislation Act 2001 dictionary entry for business day, opened before the days are counted.

Example of the limit. A contract that makes the progress payment payable on day 10 is earlier than 15 business days after the claim. Section 13 uses that earlier day. The ACT Government page states the same earlier-of test.

Stop and hand it back when

  • A 20-business-day subcontract due date from New South Wales is used. Section 13 states 15 business days, or the earlier contractual day.
  • The penalty-unit values in the republication note, $160 for an individual and $810 for a corporation, are used as a minimum or maximum for the claim.
  • Business days are counted without opening the Legislation Act dictionary. This Act’s dictionary adds only that a business day does not include 27 to 31 December.

Sources for this task were checked on 2026-09-22.

Who does what

Who does what
RoleWhat they do
AssistanceSupporting preparation only. Extract the calendar month, the claimed amount, the contract payment day and the description of the work into a checking list. Substantive advice, judgement and any restricted content remain with the responsible human.
LawyerPerform the substantive analysis and decisions. Independently check any permitted supporting work and approve the exact output for its intended use.

Checklist

  1. Open Republication No 14 and section 9. Apply the stated exclusions, including a resident owner’s insurable residential building work to the extent the contract relates to a building where that owner lives or intends to live. A resident owner does not include a person who is or should be licensed as an owner-builder. Work outside the ACT is outside the Act to that extent.
  2. Apply section 15 to the day the claim is given: on or after the last day of the calendar month, an earlier day provided in the contract, or the day of termination. Keep it before the later of the contract period and 12 months after the work or related goods and services were last supplied. Give no more than one payment claim for each calendar month unless the contract provides for more.
  3. Check that the claim identifies the construction work or related goods and services, states the claimed amount, and states that it is made under the Act.
  4. Take the due date from section 13: the earlier of 15 business days after the payment claim is given, and the day the payment becomes payable under the contract. Before counting, open the Legislation Act dictionary definition of business day. This Act adds that a business day does not include 27 to 31 December.

Sources

Suggested working checks from the linked public source. Read that source before you rely on the check. This is not a record that the check has been done.