Check a delay and variation summary against the programme

Key facts

Human involvement
YellowClose supervision
How AI is used
Set the summary beside the programme and the site records and list each date, activity, or quantity that does not match, with the document name. Do not write a delay analysis or a claim letter.
What the lawyer must review
Entitlement to time or money is the contract’s clause, which the lawyer reads. 31 U.S.C. § 3905’s 7-day payment duty, on an agency construction contract, runs from satisfactory performance and from amounts the agency has paid the prime. It is not a test of who caused delay. 40 U.S.C. § 3133’s 90-day notice and one-year suit limit apply to a bond claim by a person who furnished labor or material, not to a delay claim between the parties. Formal Opinion 512 requires the lawyer to verify the tool’s dates before they are used.
Written for / version
United States versionUS

Who does what

Who does what
RoleWhat they do
AssistanceConsider narrowly defined preparation support after confirming the tool’s capability and permitted scope.
LawyerSet the scope, supervise the work closely, verify every part relied on, resolve omissions and exceptions, and approve the exact output.

Checklist

  1. Trace every relied-on figure to its source, confirm dates and assumptions, and independently recalculate totals or derived amounts.
  2. Review operative clauses in the complete document, including definitions, cross-references, schedules and inconsistencies with the instructions.
  3. Confirm the output against the client’s instructions and the complete relevant source material, including omissions or contradictions.
  4. Resolve exceptions and record the responsible lawyer’s approval of the exact output and intended use.