# Prepare a variation or extension-of-time claim from the site records

> From the contract, site diaries, programmes and correspondence, draft a variation or EOT claim with a chronology, clause references and a list of missing records.

Canonical page: https://ailawframework.com/practice/construction-and-infrastructure/prepare-a-variation-or-extension-of-time-claim-from-the-site-records  
Last reviewed: 2026-10-22

Site index for agents: https://ailawframework.com/llms.txt

## Key facts

| Fact | Value |
| --- | --- |
| Practice area | [Construction & Infrastructure](https://ailawframework.com/practice/construction-and-infrastructure.md) |
| Human involvement | Yellow: Lawyer and AI draft together |
| How AI is used | From the contract, site diaries, programmes and correspondence, draft a variation or EOT claim with a chronology, clause references and a list of missing records. |
| What the lawyer must review | Check notice and time-bar clauses; missing them is fatal Check the claim against the actual clause and contemporaneous records |
| Written for / versions | 1 jurisdiction versions below |

## Checking plan

**Source-by-source verification**

Trace relied-on content to independent sources and check for relevant material the output has missed.

- What the AI does: Potential support includes preparing preliminary structure or wording and summarising source material. Confirm the tool’s capability and permitted scope.
- What the lawyer does: Set the scope, verify the evidence, resolve exceptions and approve the final output for its intended use.
- Who reviews: Responsible lawyer with competence in the matter
- Basis: Suggested checking approach based on the task guidance. Complete the assessment for the actual tool, information and jurisdiction.
- Why: The plan reflects the described work and review requirements. Policy colours are not used to determine permission or checking.

## Checks the lawyer makes

1. Open each relied-on authority independently. Confirm its existence, current status, proposition and any quotation or pinpoint reference.
2. Trace every relied-on figure to its source, confirm dates and assumptions, and independently recalculate totals or derived amounts.
3. Calculate operative dates independently from the current rule and actual triggering event. Check exceptions and record the verified deadline.
4. Review operative clauses in the complete document, including definitions, cross-references, schedules and inconsistencies with the instructions.
5. Confirm that the wording reflects the client’s instructions and contains no unintended admission, concession or commitment. Check the recipient and tone.
6. Verify dates, people and sequence against contemporaneous records. Preserve uncertainty and identify gaps or conflicting accounts.
7. Verify the applicable jurisdiction and the version of each relevant law, rule or instrument in force at the material time.
8. Confirm the output against the client’s instructions and the complete relevant source material, including omissions or contradictions.
9. Resolve exceptions and record the responsible lawyer’s approval of the exact output and intended use.

## Notes

- Confirm the required checking with the responsible lawyer before work starts. The checking approach does not establish permission to use AI.

## Jurisdiction versions

| Jurisdiction | Level |
| --- | --- |
| [United States](https://ailawframework.com/practice/construction-and-infrastructure/prepare-a-variation-or-extension-of-time-claim-from-the-site-records/united-states.md) | Yellow |

*Practice guidance for planning and review. Confirm current primary sources and the requirements of the actual matter. This is general information, not legal advice.*