# List site-record facts for a response to a contracting officer's decision

> From the site records, list the dates, quantities, and amounts that relate to each reason in the decision, with the page. Write no sentence of an appeal or a complaint.

Canonical page: https://ailawframework.com/practice/construction-and-infrastructure/draft-a-security-of-payment-adjudication-response-from-the-site-records/united-states  
Last reviewed: 2026-10-22

Site index for agents: https://ailawframework.com/llms.txt

## Key facts

| Fact | Value |
| --- | --- |
| Practice area | [Construction & Infrastructure](https://ailawframework.com/practice/construction-and-infrastructure.md) |
| Human involvement | Red: Lawyer writes; AI may check, clarify or collect data |
| How AI is used | From the site records, list the dates, quantities, and amounts that relate to each reason in the decision, with the page. Write no sentence of an appeal or a complaint. |
| What the lawyer must review | Section 7103(d) and (e) require the contracting officer's decision to be in writing, to state the reasons, and to inform the contractor of the rights in the chapter. Specific findings are not required, and if made they are not binding later. Section 7104(a) allows an appeal to the agency board within 90 days from receipt of the decision. In lieu of that appeal, § 7104(b) allows an action in the United States Court of Federal Claims, filed within 12 months from receipt, proceeding de novo. An action against the Tennessee Valley Authority goes to a district court under 28 U.S.C. § 1337, also within 12 months. You choose the forum and you write the paper. The list does not. |
| Written for | United States |
| Applies to | [Draft a security-of-payment adjudication response from the site records](https://ailawframework.com/practice/construction-and-infrastructure/draft-a-security-of-payment-adjudication-response-from-the-site-records.md) |

## Checking plan

- What the AI does: From the site records, list the dates, quantities, and amounts that relate to each reason in the decision, with the page. Write no sentence of an appeal or a complaint.
- Basis: Checked against the linked sources on 22 October 2026. Confirm the current instrument before reliance.

## Notes

- The 90 days and the 12 months both run from receipt of the contracting officer's decision.
- A board appeal and a Court of Federal Claims action are alternatives. The Tennessee Valley Authority path is a district court.

## Sources

- [41 U.S.C. § 7103, Decision by contracting officer](https://www.law.cornell.edu/uscode/text/41/7103) (checked 2026-10-22)
- [41 U.S.C. § 7104, Contractor’s right of appeal](https://www.law.cornell.edu/uscode/text/41/7104) (checked 2026-10-22)

*Practice guidance for planning and review. Confirm current primary sources and the requirements of the actual matter. This is general information, not legal advice.*